Question: Lead is the amount of time that the project team gives to a successor task to get started before the predecessor task is finished. Lag
Lead is the amount of time that the project team gives to a successor task to get started before the predecessor task is finished. Lag time is the amount of time delay that the project team gives between the predecessor and successor tasks . Adjusting leads and lags is done in one of the below processes, which is A. Schedule compression.
B. Schedule development.
C. Define activities.
D. Sequence activities.