Question: Natalie is the project manager working in a matrix organization. She reports to PMO, which has many projects. Her project work is part of a
Natalie is the project manager working in a matrix organization. She reports to PMO, which has many projects. Her project work is part of a program. She is performing the task, as defined in the project management plan. The process is called?
A. Direct and manage project work.
B. Perform integrated change control.
C. Monitor and control project work.
D. Close project.