Question: Martha is the senior project manager. She is working on the project which has multiple iterations. Currently, she is involved in the process which compares

Martha is the senior project manager. She is working on the project which has multiple iterations. Currently, she is involved in the process which compares the actual performance against the planned outcome in the project management plan and if there is any variation from the plan, the variation is corrected through corrective action by the change control process.

Identify the process.

A. Direct and manage project work.

B. Perform integrated change control.

C. Monitor and control project work.

D. Close project.