Question: On Pauls project, the earned value (EV) is $1,115 and the actual cost (AC) is $1,100. What is the cost variance (CV)? A. $2,215 B.
On Paul’s project, the earned value (EV) is $1,115 and the actual cost
(AC) is $1,100. What is the cost variance (CV)?
A. $2,215 B. 1.0136 C. -1%
D. * $15