Question: Outputs from the Estimate Activity Resources process include: A. Job descriptions of resources required for the project. B. Salary schedules for various project resources. C.
Outputs from the Estimate Activity Resources process include:
A. Job descriptions of resources required for the project.
B. Salary schedules for various project resources.
C. * Identification of the types and quantities of resources required for each activity in a work package.
D. Analogous estimates of resource requirements for each work package and each work period.