Question: Outputs from the Plan Risk Responses process include all of the following EXCEPT: A. Change requests. B. * Corrective actions. C. Project documents updates. D.
Outputs from the Plan Risk Responses process include all of the following EXCEPT:
A. Change requests.
B. * Corrective actions.
C. Project documents updates.
D. Project management plan updates.