Question: The original schedule (for a project, a work package, or an activity), plus or minus approved changes, is called: A. The working schedule B. The

The original schedule (for a project, a work package, or an activity), plus or minus approved changes, is called:

A. The working schedule B. The target schedule C. The performance schedule D. * The schedule baseline