Question: Plan Risk Responses is intended to: (a) Create steps to identify project risks (b) Formulate strategies for dealing with adverse events (c) Construct a list
Plan Risk Responses is intended to:
(a) Create steps to identify project risks
(b) Formulate strategies for dealing with adverse events
(c) Construct a list of previous project risks
(d) Develop measurements to quantify project risks