Question: According to the PERT calculation, what is the standard deviation for the 3-point estimate of the following activity? Optimistic: 4 days; most likely: 5 days;
According to the PERT calculation, what is the standard deviation for the 3-point estimate of the following activity?
Optimistic: 4 days; most likely: 5 days; pessimistic: 10 days
(a) 1 day
(b) 5 days
(c) 5.67 days
(d) 6 days