Question: Precedence diagramming method is also known as activity on node. In this diagram, activities are done on node. This diagram displays the logical and sequential
Precedence diagramming method is also known as activity on node. In this diagram, activities are done on node. This diagram displays the logical and sequential activities in the project.
Activities are shown in rectangle and the relationships are shown in arrows. Charlie is working on this diagramming method. And his manager Victor asked him about the relationships available in the Precedence diagramming method. Charlie explained to him the valid relationships available in the diagram. One of the options given below is not a valid relationship in the precedence diagramming method, which one is it?
A. Start-to-Start.
B. Finish-to-Start.
C. Start-to-End.
D. Finish-to-Finish.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts