Question: Project Scope Baseline consists of ____ A. Statement of work and WBS B. Scope Management Plan, Scope Statement, and WBS C. Scope Management Plan, WBS,
Project Scope Baseline consists of ____ A. Statement of work and WBS B. Scope Management Plan, Scope Statement, and WBS C. Scope Management Plan, WBS, and WBS Dictionary D. * Scope Statement, WBS, and WBS Dictionary