Rambo is a recently hired Six Sigma expert. Kadir is the process owner of the process Rambo must optimise. During the project kick-start meeting with the project sponsor, Kadir said he supports all continuous improvement efforts. However, Kadir is unaware of the Six Sigma technique and feels threatened by the newly hired expert, and as a result, is blocking Rambo’s ideas. What is Kadir’s current engagement level with the project?
A. Unsupported B. * Resistant C. Supportive D. Neutral