Question: Simon is managing a simple project that involves painting the inside of a square room. On this project, only four walls will be painted. The
Simon is managing a simple project that involves painting the inside of a square room. On this project, only four walls will be painted. The project will last four days and one wall a day will be painted at the budgeted cost of $50 per wall. At the end of day 2, Simon reports the following status: 3 walls are complete and, so far, the total expenses are
$120.The project is A. ahead of schedule and over budget.
B. * ahead of schedule and under budget.
C. behind schedule and under budget.
D. behind schedule and over budget.