Question: Stanley is working on the Project Quality management related processes. Stanley is reporting to the PMO directly. The process which Stanley is working on is
Stanley is working on the Project Quality management related processes. Stanley is reporting to the PMO directly. The process which Stanley is working on is used to find the project activities which are in compliance with organizational standards, policies, procedures regularly. This process is called?
A. Quality Audit.
B. Quality control.
C. Quality review.
D. Quality Assurance.