Question: Tech Systems is an innovative technology company using artificial intelligence in their reject project. They are making robots for some of the automation work. Charles
Tech Systems is an innovative technology company using artificial intelligence in their reject project. They are making robots for some of the automation work. Charles is working as a project manager in this project and deals with resource allocation, examining alternative project approaches, and managing the interdependencies in the project. One of the given options is not valid output in project integration management, identify which.
A. Project charter, Deliverables.
B. Project management plan, approved change requests.
C. Change requests, work performance report.
D. Scope management plan.