Question: The critical path for a project is that sequence of dependent tasks that have the largest sum of most likely durations. The critical path determines
The critical path for a project is that sequence of dependent tasks that have the largest sum of most likely durations. The critical path determines the earliest possible completion date of a project.
A. * True B. False