Question: The critical path for a project is that sequence of dependent tasks that have the shortest sum of pessimistic durations. The critical path determines the
The critical path for a project is that sequence of dependent tasks that have the shortest sum of pessimistic durations. The critical path determines the latest possible completion date of a project.
A. True B. * False