Question: The critical path is established by calculating the following dates: A. Start-to-start, start-to-finish, finish-to-finish, finish-to-start. B. * Early start, early finish, late start, late finish.
The critical path is established by calculating the following dates:
A. Start-to-start, start-to-finish, finish-to-finish, finish-to-start.
B. * Early start, early finish, late start, late finish.
C. Predecessor-to-successor, predecessor-to-predecessor, successor-to-
successor.
D. Primary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-finish.