Question: There are several executing activities underway on your project. You are beginning to get concerned about the accuracy of the progress reporting your team members

There are several executing activities underway on your project. You are beginning to get concerned about the accuracy of the progress reporting your team members are doing. How could you verify whether there is a problem?

A. * Perform a quality audit.

B. Create risk quantification reports C. Perform regression analysis D. Perform Monte Carlo analysis