Question: Two team members are having an argument over priorities in your project. One thinks that you should write everything down before you start doing any

Two team members are having an argument over priorities in your project. One thinks that you should write everything down before you start doing any work, while the other thinks you can do the work while you finish the documentation. You sit both of them down and listen to their argument. Then you decide that you will write most of it down first but will start doing the work when you are 80% done with the documentation. What conflict resolution technique are you using?

A. Forcing B. Confronting C. Smoothing D. * Compromise