Question: Upon evaluation, a newly appointed project manager identifies that the XYZ project has many risks with high-riskimpact scores, but has an overall low risk score.

Upon evaluation, a newly appointed project manager identifies that the XYZ project has many risks with high-riskimpact scores, but has an overall low risk score. How is this possible?

A. The risk scores are graded on a bell curve.

B. The risks are rated High, Medium, and Low C. The impact of each risk is not accounted for until it comes to fruition D. * The probability of each risk is low