Question: What are the procedures to find the critical path on a network diagram? A. Draw the network diagram B. Identify all paths in the network

What are the procedures to find the critical path on a network diagram?

A. Draw the network diagram B. Identify all paths in the network diagram C. Find the duration of each path D. The path with the largest duration is the critical path E. * All of the above