Question: What is Critical Path Analysis A. * A project management technique for process planning that defines critical (milestones) and non-critical tasks B. A graphical display
What is Critical Path Analysis A. * A project management technique for process planning that defines critical (milestones) and non-critical tasks B. A graphical display of project activities represented by an area of land showing physical features C. A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site D. A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project