Question: When an organization is in the process of procurement, it can either prepare its own cost estimates or have an outside professional estimator prepare a
When an organization is in the process of procurement, it can either prepare its own cost estimates or have an outside professional estimator prepare a cost estimate. This estimate is a:
A. Market estimate B. Accurate estimate C. True estimate D. * Benchmark estimate