Question: which is/ are correct A. * Precedence Diagramming Method is more popular than the Arrow Diagramming Method B. * Arrow Diagramming Method shows can only

which is/ are correct A. * Precedence Diagramming Method is more popular than the Arrow Diagramming Method B. * Arrow Diagramming Method shows can only show finish-to-start dependencies C. Precedence Diagramming Method uses arrows to represent activities D. Precedence Diagramming Method may require dummy activities to define relationships