Question: Which statement about CPM is FALSE? A. It is possible to have multiple critical paths in project scheduling B. It is the path consisting of
Which statement about CPM is FALSE?
A. It is possible to have multiple critical paths in project scheduling B. It is the path consisting of the tasks that will take the most time to complete C. The slack time of a task is the amount of time that it can be delayed without disrupting the entire project D. * It cannot identify tasks that can be done in parallel