Question: Which statement about CPM is FALSE? A. It is possible to have multiple critical paths in project scheduling B. It is the path consisting of

Which statement about CPM is FALSE?

A. It is possible to have multiple critical paths in project scheduling B. It is the path consisting of the tasks that will take the most time to complete C. The slack time of a task is the amount of time that it can be delayed without disrupting the entire project D. * It cannot identify tasks that can be done in parallel

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock