Question: You are currently in the planning process and have identified the risks associated with this project and are ready for the next step. What is

You are currently in the planning process and have identified the risks associated with this project and are ready for the next step. What is the next step?

A. * Assign probability and impact values using qualitative or quantitative analysis B. Use the Delphi technique to confirm the identified risks C. Identify the response strategies for the identified risks D. Start working on the creation of the project schedule