Question: You are managing a construction project. You are currently estimating the duration of a very critical activity. You have gathered the following information from the

”You are managing a construction project. You are currently estimating the duration of a very critical activity. You have gathered the following information from the experts:Best case scenario: Activity can take 3 days to complete.Worst case scenario: Activity may take up to 12 days to complete.Likely scenario: 6 days to complete such activitiesUsing Three-Point Analysis, what is the expected time?

A. * 7 days B. 5 days C. 12 days D. No able to determine with this information