Question: You are managing a new technology project designed to improve the removal of hazardous waste from your city. You are in the planning phase of
You are managing a new technology project designed to improve the removal of hazardous waste from your city. You are in the planning phase of this project and have prepared your network diagram. Your next step is to-
A. * Describe any unusual sequencing in the network B. State the number resources required to complete each activity C. Establish a project calendar and link it to individual resource calendars D. Determine which schedule compression technique is the most appropriate, because your customer requests that the project be completed as soon as possible