Question: You are the project manager for Changing Tides video games. You have gathered the inputs for the Estimate Activity Durations process. Which of the following
You are the project manager for Changing Tides video games. You have gathered the inputs for the Estimate Activity Durations process. Which of the following tools and techniques will you employ to produce the outputs for this process?
A. Activity list, expert judgment, alternatives analysis, analogous estimating, parametric estimating, three-point estimates, and reserve analysis B. Activity list, expert judgment, analogous estimating, parametric estimating, and threepoint estimates C. Expert judgment, analogous estimating, parametric estimating, three-point estimates, and reserve analysis D. Expert judgment, alternatives analysis, analogous estimating, parametric estimating, and three-point estimates