Question: You are the project manager for Changing Tides video games. You have produced a project schedule network diagram and have updated the activity list. Which
You are the project manager for Changing Tides video games. You have produced a project schedule network diagram and have updated the activity list. Which process have you just finished?
A. The Define Activities process, which identifies all the specific activities of the project B. The Sequence Activities process, which identifies all the activity dependencies C. The Develop Schedule process, which diagrams project network time estimates D. The Estimate Activity Durations process, which estimates activity durations
Step by Step Solution