Question: You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for
You are the project manager working on a research project for a new drug treatment.
Your preliminary project schedule runs past the due date for a federal grant application.
The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of ___________________.
A. crashing B. fast tracking C. resource leveling D. adjusting the resource calendar