Question: PART-A: Choose the most appropriate answer from listed options (a, b, c or d), and provide an explanation so that your answer is recognized as
PART-A:
Choose the most appropriate answer from listed options (a, b, c or d), and provide an explanation so that your answer is recognized as complete.
(Weigh 60)
1. You can not start editing a technical report until someone else completes the first draft of related document. The type of dependency is:
a. Finish to Start
b. Start to Start
c. Finish to Finish
d. Start to Finish
2. You are Project Manager working on research project for a new drug treatment in the country. The preliminary project schedule runs past the due date for a federal application. The Manager of R and D department has agreed to release two resources work on your project in order to meet the federal grant application. It means:
a. Crashing
b. Fast tracking
c. Resource levelling
d. Adjusting the resource calendar
3. What is the preferred order for performing testing on ICT project?
a. Unit testing, integration testing, system testing, user acceptance testing
b. Unit testing, system testing, integration testing, user acceptance testing
c. Unit testing, system testing, user acceptance testing, integration testing
d. Unit testing, integration testing, user acceptance testing, system testing
4. What is the lowest level of Work Breakdown Structure decomposition?
a. Work package
b. Deliverables
c. Sub deliverables
d. Project alone
Step by Step Solution
There are 3 Steps involved in it