Question: You have just returned from the weekly change control board meeting where you presented the requested changes to the employee move project. Five changes were
You have just returned from the weekly change control board meeting where you presented the requested changes to the employee move project. Five changes were approved, but one was denied. You are now updating the project management plan to incorporate the changes. In which project management process would this be done?
A. Planning B. * Direct and Manage Project Work C. Monitor and Control Project Work D. Executing