Question: You have received the following estimates for a complex activity that is critical to the success of your project. The most likely estimate is $42,

You have received the following estimates for a complex activity that is critical to the success of your project. The most likely estimate is $42, the optimistic estimate is $35, and the pessimistic estimate is $54. What is the expected activity cost of this activity (rounded to the nearest dollar)?

A. 49 B. 39 C. 43 D. 41