Question: You have received estimates for activity costs associated with one work package of the WBS. Additional contingencies have been added to the estimates to account

You have received estimates for activity costs associated with one work package of the WBS. Additional contingencies have been added to the estimates to account for cost uncertainty.

Which of the following tools and techniques of Estimate Costs does this describe?

A. Reserve analysis B. Three-point estimates C. Vendor bid analysis D. Analogous estimates