Question: You know that BAC = 500, PV = 325, cumulative AC = 275, and cumulative EV = 250 and that you are experiencing typical variances.

You know that BAC = 500, PV = 325, cumulative AC = 275, and cumulative EV = 250 and that you are experiencing typical variances. What is ETC?

A. 227.3 B. 250 C. 274.7 D. 525