Question: You want to improve your activity cost estimates by taking into account estimation uncertainty and risk. Which of the following tools and techniques will you
You want to improve your activity cost estimates by taking into account estimation uncertainty and risk. Which of the following tools and techniques will you use?
A. Analogous estimates B. Three-point estimates C. Parametric estimates D. Bottom-up estimates