Question: Your earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much: A.
Your earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:
A. Higher than the cumulative AC.
B. Higher than the cumulative PV.
C. * Lower than the cumulative PV.
D. Lower than the cumulative CPI.