Question: Your earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much: A.

Your earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:

A. Higher than the cumulative AC.

B. Higher than the cumulative PV.

C. * Lower than the cumulative PV.

D. Lower than the cumulative CPI.