Question: Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the proper change control process. The WBS changes might
Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the proper change control process. The WBS changes might in turn require which of the following? Choose the best answer.
A. Scope changes B. Cost changes C. Schedule revisions D. Risk response changes