Question: Your project is progressing as planned. The project team has come up with a demo that the sales team will use when making presentations to
Your project is progressing as planned. The project team has come up with a demo that the sales team will use when making presentations to prospective clients. You will do which of the following at your next stakeholder project status meeting? Choose the best answer.
A. Preview the demo for stakeholders, and obtain their approval and sign-off.
B. Report on the progress of the demo, and note that it’s a completed task.
C. Review the technical documentation of the demo, and obtain approval and sign-off.
D. Report that the demo has created a change request that’s been documented in the change control system.