Question: Repeat exercise 9, assuming activities E, F, and L are performed by the same crew and the contractor has only one crew.Will the project completion
Repeat exercise 9, assuming activities E, F, and L are performed by the same crew and the contractor has only one crew.Will the project completion date be delayed?
If yes, by how many days?