Question: The latest finish time for an activity is found during the backward pass through the network. The latest finish time is equal to a. the
The latest finish time for an activity is found during the backward pass through the network. The latest finish time is equal to
a. the largest LF of the activities for which it is an immediate predecessor.
b. the smallest LF of the activities for which it is an immediate predecessor.
c. the largest LS of the activities for which it is an immediate predecessor.
d. the smallest LS of the activities for which it is an immediate predecessor.
Step by Step Solution
3.46 Rating (153 Votes )
There are 3 Steps involved in it
The latest finish time for an activity is found during the backward pass through the networ... View full answer
Get step-by-step solutions from verified subject matter experts
