Question: 5. The latest finish time for any activity is equal to minimum of the start times of all of its immediate successors. --- True/False 6.

5. The latest finish time for any activity is equal to minimum of the start times of all of its immediate successors. --- True/False

6. Critical path length (CPL)is the least amount of time required to complete a project -- True/False

7. The forward pass calculations will help you determine the length of the critical path length. --True/False

8. The backward pass calculations will help you determine the slacks of the activities and thereby facilitate the identification of critical and non-critical activities. --- True/False