Question: Consider the information provided below for the project and answer the following questions. Activity Predecessor Duration (in days) A - 3 B A 4 C

Consider the information provided below for the project and answer the following questions.

Activity

Predecessor

Duration (in days)

A

-

3

B

A

4

C

A

5

D

B, C

2

E

B, C

3

F

D, E

4

Question 6 options:

12345678910111213141516

What is the slack time, in days, associated with activity D?

12345678910111213141516

Suppose that additional resources are provided to crash the project completion time below its expected normal completion time. Which activities would be potential candidates for crashing?

12345678910111213141516

Determine the latest finish time (LF) of activity B.

12345678910111213141516

Determine the earliest start time (ES) of activity E.

12345678910111213141516

What is the slack time, in days, associated with activity E?

12345678910111213141516

What is the critical path?

12345678910111213141516

How long will take to complete the project?

12345678910111213141516

Determine the latest start time (LS) of activity B.

12345678910111213141516

Determine the latest finish time (LF) of activity B.

12345678910111213141516

Determine the latest start time (LS) of activity E.

1.

ACEF

2.

ABEF

3.

16 days

4.

15 days

5.

14 days

6.

2

7.

0

8.

1

9.

4

10.

5

11.

8

12.

10

13.

A

14.

C

15.

F

16.

E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!