Question: A given project's expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on
A given project's expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on or before 28 days. The project's statndard deviation along its critical path 2.03. The approximate computed z value is:
a. 4.66
b. 1.00
c. 0.76
d. 2.71
Step by Step Solution
3.49 Rating (152 Votes )
There are 3 Steps involved in it
To find the probability that the project will finish on or before 28 days we need to compute the ... View full answer