Question: A given project's expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on

A given project's expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on or before 28 days. The project's statndard deviation along its critical path 2.03. The approximate computed z value is:

a. 4.66

b. 1.00

c. 0.76

d. 2.71

Step by Step Solution

3.49 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To find the probability that the project will finish on or before 28 days we need to compute the ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

609926b295d4d_29421.pdf

180 KBs PDF File

Word file Icon

609926b295d4d_29421.docx

120 KBs Word File

Students Have Also Explored These Related Mathematics Questions!