Question: A given project's expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on

 A given project's expected duration along its critical path is 22.5

A given project's expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on or before 28 days. The project's standard deviation along its critical path is 2.03. The approximate computed z value is: 4.66 1.00 0.76 2.71