A project is in its 50th week and has an actual cost of $300,000 for the work
Fantastic news! We've Found the answer you've been seeking!
Question:
A project is in its 50th week and has an actual cost of $300,000 for the work performed to date. The budgeted cost of that work is $400,000. It expected to have completed $500,000 worth of work by this time. The budget for the entire project is $1,000,000. What is the:
a. CV
b. SV
c. CPI
d. EAC (provide two possible values. Show the formulas you use in calculating each)