Question: Based on the data below answer these questions: a) What is the total duration of the project? b) Which activities are part of the critical
Based on the data below answer these questions:
a) What is the total duration of the project?
b) Which activities are part of the critical path?
c) What are the Cost Performance Index (CPI) and Schedule Performance Index (SPI) of the project at the end of week seven? Provide short comments on the situation of the project.
d) Calculate the Estimated cost at completion (EAC).

Activity ABUAHE D F Predecessors None A A A and C Duration Budget Actual Cost (weeks) USD 2 25 5 4 - 3 4 2 120 200 160 140 210 80 USD 130 150 160 10 20 0 % Complete 100 80 100 10 20 0
Step by Step Solution
3.42 Rating (165 Votes )
There are 3 Steps involved in it
To solve these problems we need to analyze the project data provided a Total Duration of the Project The total duration of the project is determined b... View full answer