Based on the data below answer these questions: a) What is the total duration of the project?
Fantastic news! We've Found the answer you've been seeking!
Question:
Based on the data below answer these questions:
a) What is the total duration of the project?
b) Which activities are part of the critical path?
c) What are the Cost Performance Index (CPI) and Schedule Performance Index (SPI) of the project at the end of week seven? Provide short comments on the situation of the project.
d) Calculate the Estimated cost at completion (EAC).
Related Book For
Accounting
ISBN: 978-0324662962
23rd Edition
Authors: Jonathan E. Duchac, James M. Reeve, Carl S. Warren
Posted Date: