Calculate the number of Kanbans needed at the ABC Company for the following two products, Produced in
Fantastic news! We've Found the answer you've been seeking!
Question:
Calculate the number of Kanbans needed at the ABC Company for the following two products,
Produced in a factory that works eight hours per day, five days per week.
| Product 1 | Product 2 |
Usage | 350/week | 200/day |
Lead time | 1 week | 2 week |
Container size | 22 units | 33 units |
Safety stock | 12 percent | 0 |